 |
|
|
Construction Updates
Relocation
Schedule
March 2010
- College Center Remodel
Walls are up and in some cases the first coat of paint has
been applied. The dining addition is complete and kitchen
equipment is being installed. The exterior structure (colonnade)
is up, along with retaining walls as site work continues. The
new parking lot is ready for pavement however, it will be a
month or so before the asphalt plant opens and can provide
asphalt to the project. The project is scheduled for
completion at the end of May and the Relocation Task Force
will convene soon to start the process of developing
the re-occupancy schedule. The furniture package is being finalized.
- College Center Remodel Phase 2 – Horizon
Hall Renovation
The project is in the design development stage. The renovation
will consist of eight new shared classrooms, group study rooms,
student and faculty break areas, storage, space for future TRIO
needs along with a number of faculty/staff/adjunct offices. The
scope of work includes new mechanical, electrical, window and
roof systems. It is anticipated that the renovation will
begin in late May 2010 and be complete by the end of May 2011.
- Public Service Institute (T&I)
Minor remodeling has occurred in this building to accommodate
Fire Science and temporary locations for those vacating Horizon
while the renovation occurs. Major construction related
to this building is on hold per the Board of Trustees.
- Signage Master Plan – Phase
1
Progress is being made to develop an exterior signage package
for the buildings on the Greeley campus. It is anticipated
that the exterior signs will be installed by the beginning
of the fall 2010 semester. The goal ( as funding is available)
is to provide a monument type sign at each of the campuses
buildings and provide a directional marquee at each entrance
to the campus.
- Cat Building Relocation Project
A Relocation Task Force has been assembled to develop a moving
schedule for the contents at the Ft. Lupton CAT building. The
plan is to relocate items from this building to the Automotive
and Technology Center and Hansen building at the conclusion
of the spring 2010 semester.
- Key Card (Smart Card) Access System
Buildings on the
Greeley campus are being retro fitted with an electronic access
system which will use a Smart Card for after hour access when
the buildings are secure. After hour access
is defined as 10:00 p.m. through 6:00 a.m. Mondays through Friday,
weekends and holidays. A Smart Card reader will be located
at the main entrance of each building. The Smart Card will
be a combination of full-time employee ID badge and a key card.
Swiping of the Smart Card will not only provide access to the
building but will unarm the security system. Stay tuned
for information about Smart Card check out procedures and training.
The Loveland and Downtown campuses already have key card access
systems.
January 2010
- Automotive and Technology Center
Occupancy
of the new building began on December 14th. The moving in process
is nearing completion in time for the return of students for
the spring semester. Please feel free to visit the new building.
- College Center Remodel
Walls are going up
and the interior spaces are beginning to take form. The parking
lot paving was delayed due to inclement weather. The
paving is scheduled to begin in mid-March. Exterior features
including hardscaping continues. The project is on track
to be complete in mid-May 2010.
- College Center Remodel Phase
2/Horizon Hall
Programming
of the building is complete with design development scheduled
to begin in late January. The plan is to have construction
documents complete by early April and start actual construction
as soon as the College Center main remodel ends. Some
minor preparation of Horizon for construction will begin in
early May 2010.
- T&I
The T&I building is cleaned
and minor cosmetic work has progressed to make this space ready
for the Wild Land Academy and Fire Science programs. Major
remodeling is on hold until the decision is made by the Board
of Trustees to proceed.
- Berthoud
The selection of an
architectural firm for the new campus is on hold until a decision
is made by the Board of Trustees to proceed.
Previous Construction Updates
|
|
|
|