 |
|
|
Construction Updates
Relocation
Schedule
November 2009
- College Center Phase 2 (Remodel of Hansen for
Classrooms)
The
steering committee is meeting with members of the design team
to review options for the remodeling of this building. The
project is still in the programming stage and is expected to
enter the design stage by the end of the year. Design is
anticipated to conclude in spring with an anticipated construction
start date towards the end of May 2010.
- Berthoud Site
The architect selection
committee has interviewed firms who met the pre-qualification
requirements. The committee is
reviewing information and gathering additional information.
- Aims
Automotive and Technology Center:
The exterior of the building is nearing completion while the
interior is being painted and outfitted with all mechanical,
electrical and plumbing equipment. The ceiling grids have been
installed and the bathrooms are completed. The Service Shop is
being outfitted with new auto lifts and the paint booths are
ready for testing. All utilities have been completed to the building
and we are waiting to get the phone service up and running. The
landscaping is 90% complete and the perimeter fencing is complete.
The building is scheduled to be completed by mid December.
- College
Center Remodel Project:
The demolition phase of the project has been completed. Plumbing,
electrical and mechanical equipment and wiring are being installed.
New metal stud wall framing is completed on the second floor
and framing is beginning on the first floor. Exterior work on
the west side of the building has begun with the concrete footer
work beginning this month. The new College Center parking lot
is progressing with the excavation to be completed by mid November.
Concrete curb and gutter work should be completed by the middle
of November with paving to be completed by the end of November
depending on weather. The College Center is expected to be completed
in May 2010.
September 2009
- Berthoud
The College is currently in the RFQ process for architectural
firms for the Berthoud Campus. The decision at this time
is to design the new campus but not yet proceed with construction.
- Horizon Hall
The design team will begin meeting with members of the steering
committee to start design in late September. The
plan is to begin construction at the end of the spring 2010
term.
- College Center Remodel:
Demolition on the inside of the College Center is nearly complete.
We are waiting for the State permit to start new construction
work inside the building. New work should begin
around the middle of September. The new south Parking Lot should
be started by the end of September and be completed by the
end of November.
- Auto Center Building:
The exterior building shell is nearly complete. All interior
building slabs have been poured and work on electrical and
mechanical systems is progressing. The roofing is nearly complete
and the first layer of asphalt on all the parking lots has
been installed. The interior framing has been completed on
the West end office/classrooms area and dry wall is being installed.
The paint booths have been installed and all interior block walls
are nearly completed.
June 2009
- College Center Remodel
The relocation of programs/personnel
out of the College Center is complete. The project is now
entering the design development phase and demolition is scheduled
to begin at the end of June. Floor
plans for the project are available for review in Beaty Hall room
127C through June 25th.
- Berthoud Master Plan
The master plan for the new site
at Berthoud is nearing completion. The
plan will be presented at the August 5th Board of Trustees meeting.
- Generator
Project
Final testing is scheduled for June 20th of the main campus backup
generators. The data center generator is complete.
- Allied Health & Sciences
Classroom Build-out:
The above ceiling mechanical systems have been completed and
are ready for engineers testing and inspections.
The electrical
has been completed, except for a delay in delivery of light fixtures,
which should be installed by June 19th.
Doors and hardware are
scheduled to be installed by June 19th. The ceiling tile is to
be installed by June 24th. Carpet in classrooms and vinyl in
hallway will be completed by June 30th. Final touch up and inspections
will be completed by July 3rd. Classroom furniture will be delivered
and installed by July 8th.All three Classrooms should be ready
for use the week of July 13th.
- Aims Auto Center Building – Windsor
Steel roof framing is being erected for the West end of the building
containing the offices and general education classrooms.
Steel joists
and decking are being completed for the 2nd level storage areas
this week. The steel roof framing and decking, for the main
portion of the building, will be started next week and completed
by mid July. Under slab utilities are scheduled to start the
middle of June and be completed by the middle of July. Concrete
interior slabs are scheduled to be poured starting the middle of
July and completed by the middle of August. Mechanical and electrical
equipment installation and rough-ins are scheduled to start the
end of June and be completed around Labor Day weekend. The concrete
curb & gutter and road base has been installed for the entry
road and the first lift of paving should be installed by June 12th depending
on the weather. Site utilities are proceeding, with the electrical
service scheduled to be completed by the middle of July and the
gas service scheduled to be completed by the middle of August.
The building construction is scheduled to be completed by the middle
of December, 2008.
May 2009
- Allied Health & Science First Floor Tenant Improvement
The mechanical and electrical rough ins have been completed.
The walls have been insulated, dry walled and painted and the
ceiling grid is going in as this article is being written.
The schedule for the next couple of weeks is to complete the
above ceiling mechanical, trim electrical and pull in IT cabling.
The construction portion of the project looks to be completed
by the middle of June.
- Auto Center Building in Windsor
All exterior concrete precast wall panels have been erected.
Preparation for structural steel is taking place this week.
Next week the steel erector is scheduled to start placing
steel beams and columns. Steel stud exterior walls are
being erected where possible. All light pole bases have
been installed. Back filling of the exterior foundation
walls should be completed this week. The structural steel
should be completed by the end of June including the roof
joists and decking. Mechanical rough ins should start the middle
of June. The entry curb, gutter and sidewalks should be installed
by the beginning of June and the first lift of asphalt should be
installed on the entry road by the middle part of June.
January 2009
- Emergency Generator Project
Back up generator for the General Services Building installed;
final preparations are in process to tie in the new generators
serving the campus with an anticipated completion date of February
14, 2009.
- Pedestrian Promenade
Design work for the new
pedestrian promenade is nearing completion. Construction
of this project is scheduled to begin in the Spring of 2009.
- College
Center Remodel
DLR Group was selected to be the architect
for this project. Programming
meetings with user groups is scheduled to occur during the late
January early February 2009 time period.
The Relocation Task Force
is meeting on a regular basis and is developing the location
schedule for those who will be relocated while the remodeling
occurs during the July 1, 2009 – July
1, 2010 time frame.
- Aims Automotive Center at Windsor
The design
for this project is complete and it is anticipated that earth
work will begin in March of 2009. Actual building
construction will occur shortly there after with an anticipated
completion date of January 1, 2009.
- Berthoud Campus Master
Plan
The finishing touches are occurring to the plan. A
presentation of the Master Plan will occur at the January 7th
at the regular Board of Trustees meeting.
October 2008
- Finishing the perimeter landscaping of Ed Beaty Hall by including
xerascaping, retaining walls and other features.
- The development of a pedestrian spine to promote an enjoyable
walking experience through the heart of the campus including
seating areas, lighting, planting beds and other features connecting
the Trades and Industries building with the west side of Ed Beaty
Hall.
- Landscaping improvements to the areas east of Westview and
north of the College Center.
- The project is set to begin in spring of 2009.
College Center Remodel
- The second improvement to the grid will be the replacement
of the back up generator. This improvement consists
of a new set of generators sized to accommodate the new
buildings recently added to the grid. The generators
will be equipped with a system that automatically starts
the generators eight seconds after a power interruption
occurs. The current generator requires manual intervention
for start up so this will be a big improvement towards
maintaining power in the event of an emergency. This project
also includes a generator specifically designated to support
the Data Center in the event of a power outage. This
project is scheduled for completion February of 2009.
There have been a number of questions concerning the remodel
of the College Center. To help provide everyone with
the basic information concerning this project, here is
a short summary:
- The College’s Capital Improvement Master Plan
identifies that planning begins this fiscal year for
the remodel of the College Center to become a “One
Stop Student Services Center”. This supports
the learning centered college by providing one central
location to meet student related services needs.
- The plan will include the relocation of Student Services
from the General Services building to the College Center.
- The selection of an architect and design team to assist
the College with programming and design is in process
and a firm should be selected by early December.
- It is anticipated that construction will begin in July
of 2009 and will occur for a period of one year.
There is a lengthy process of pre-planning before any
construction occurs. In addition to meeting with appropriate
faculty, staff and administrators to develop programming
requirements, a “College Center Relocation Task Force”,
will be created to help develop a schedule of possible
moving times and locations for those who will be temporary
relocated while the construction occurs. Vacating the space
will help insure that student/faculty/staff safety is maintained
during the construction process. It is anticipated that
relocation will begin at the end of spring semester 2009.
The planning process has just begun so I will be working
with administrators to develop the relocation task force
in the near future.
Greeley Campus Power Grid Improvements
- There
are two improvements to the power grid currently underway. The
first improvement will be the installation of varmint protection
on the power pole located to the north of the T&I building. The
power pole at this location provides most of the electricity
to the campus and has experienced a number of interruptions
due to squirrels and other animals making contact with
conductors and causing outages. Although there is no
way to keep animals completely away from this area,
safeguards will be installed to make it more difficult
for animals to make contact with the conductors. This
project will be complete by the end of October.
August 2008
- Design development still in process for the Automotive Technology
Building at Iron Mountain. A preliminary design and site plan
were presented at the last Board of Trustees meeting.
- Berthoud Site Development Plan is in progress with members
of the local community and Senior Management providing input
as to possible programs offered in the future. The Board
of Trustees were presented with an overview and the last BOT
meeting.
- Work will begin soon on the replacement of the College’s
backup generator. The project will consist of installing
a new systems sized to support the new buildings and future growth. A
separate generator will be installed at the General Services
building to provide backup electricity for the data center.
July 2008
- Master Drainage Plan – Work has begun to enlarge the
retention pond located west of the Hansen building and the drainage
swale located at the west property line of the College. Work
is scheduled to be complete in early July.
- Utility Master Plan Phase 1 – Plans are in place to replace
the emergency generator and install a separate generator for
the General Services building. It is anticipated that work
will begin in August and progress until December.
- Design work has started for the new Automotive Technology building
at Iron Mountain.
- Site Planning is underway for the new Berthoud Campus.
|
|
|
|